May 8, 2018 Our Parking lot construction is well underway. Here are pictures and videos to follow the progress.
Subject: Christ The Good Shepherd Weekly Update 5-04-18
Team, Here is a quick update on the project. 4/30/18 – 5/04/18 · Start paving Demo @ phase 1. · Sawcut & demo @ K of C parking lot. · Install temporary fence panels around phase 1. · Remove fence at the playground. · Start tree demo starting at the playground. · Set-up office trailer. · Set-up SWPPP.
[*] 5/07/18 – 5/11/18 · Cont. tree demo & haul off. · Start excavation and installing storm sewer line starting from detention pond.
Subject: Christ The Good Shepherd Weekly Update 5-12-18
Team,
Here is a quick update on the project. See the attached project photos.
5/7/18 – 5/11/18
· Continue tree demo & haul off. · Start excavation and installing storm sewer lines and installing M/H from the detention pond.
Subject: Christ The Good Shepherd Weekly Update 6-15-18
6/11/18 – 6/15 /18
Continue proof-rolling and identifying pumping areas, excavate and fill back in with dry soils at 8” lifts.
Completed the underground electrical to the light poles.
Install the 24” RCP with the P-Set @ the two approaches.
Trench and installed two 4” PVC conduits for future Comcast fiber line.
Trench and installed 6” PVC sleeves for irrigation @ each approach.
Install fly-ash lime, watering down with a water tank truck and mixing.
MTEC lab took densities on all areas of paving in phase 1, all passed.
Final grading to the blue top and Burts Construction completed work in phase 1.
A final proof-roll was performed in phase 1 with Richard Ghanem here to witness before Burts Construction de-mobilize, all passed.
Next Week 6/18/18 – 6/22/18
BCS field engineer starts laying out the parking lot site.
Start edge forms to paving areas.
Drill light pole piers and pour concrete.
Forner Electric to make the final connection to the underground electrical PVC to light pole bases.
Set expansion joints and rebar to paving
Drill and dial into the pour back stripe in front of the Knights of Columbus area.
Team, Here is a quick update on the project. See attached project photos.
9/10/18 – 9/14/18 1. Continue concrete pavement, sidewalk & utility demo & haul off in phase 2. Continue excavating and installing storm line, inlets & M/H in phase 2.
Team, Here is a quick update on the project. See attached project photos.
9/24/18 – 9/28/18 Excavate and install 24” RCP, type D-1 Inlet & PSET RC -type II at approaches. Continue Hauling off underground utility spoils. Continue cutting for subgrade. Rain-out days this week are from 9-24-18 thru 9-27-18. 9-28-18 was a mud day.
10/1/18 – 10/5/18 Continue cutting for sub-grade. Stockpile sub-grade materials. Blue top sub-grade.